Dendrobium Mine Plan

This timeline contains information of Dendrobium Mine current plan.
  • Timeline item 1 - complete

    Longwall 19A (Area 3A)

    Extraction of LW19A commenced on 2 November 2023 and was completed on 28 June 2024.

  • Timeline item 2 - active

    Longwall 22 (Area 3C)

    On 10 August 2024 we commenced extracting from LW22. We expect this to be completed by approximately Q4 2025

  • Timeline item 3 - incomplete

    Longwall 21A (Area 3C)

    LW21A will commence after the completion on LW22.

  • Timeline item 4 - incomplete

    Longwall 23 (Area 3C)

    LW23 will commence after the completion of LW21A.